$11,192,944
11/30/2008
This contract entailed a runway extension with installation of a new Instrument Landing System and Approach Lighting System to enhance safety. In addition to the primary runway work, this project included construction of a 510-foot-long, two-lane tunnel under the runway extension in response to the Federal Aviation Administration mandated regulations. While the project was bid on the basis of twelve-month construction term, the substantial completion had to be moved up 3 months when the FAA decided they would require that time for testing and inspection of the airfield’s new electrical components.